Project development (including project financing) construction and operation of natural gas/oil fired steam boiler with 110 t/hr steam capacity.
| Project Sponsor | SINERGY Ltd. (Hungary) |
| Development Period | 13 Months (February 2008 - March 2009) |
| Main Vendors | Ganz Danubius Hungarosteel (Hungary) |
| Project Value | 8,3 MEUR |
| Project Location | TVK Chemical Plant, Tiszaújváros, Hungary |
| Project Status | Commissioned and completed in 2009. |