EBP developed several potential Geothermal projects in Hungary, identified the potential sites and prepared the Pre-feasibility Studies, Business Plan and package it for a typical project at Álmosd, with possibility to repeat it at six other identified sites as an investment portfolio. Total renewable energy production capacity overtakes at least 10 MWe electricity and 30 MWth heat generation and cumulative CO2 emission saving is more than 130 ktons per annum.
Project Sponsor | EBP European Biopower Ltd. (Hungary) |
Development Period | 24 Months (July 2007 - June 2008) |
Main Vendors | ORMAT (Israel) |
Project Value | 75 MEUR |
Project Location | Álmosd, Hungary |
Project Status | On hold in 2009 |