Turn-key construction of a single unit extension to the plant consisting of a lignite fired steam boiler and turbine-generator set (157MW electric power capacity), Coal Handling System, Flue Gas Desulphurization Plant, Raw Water Supply System and Water Treatment Plant.

Project SponsorTurkish Electricity Generation and Transmission Corporation (Turkey)
Development Period48 Months (June 1996 - June 2000)
Main VendorsConsortium of Transelektro Ltd. (Hungary), Mitsubishi Heavy Industries (Japan), Siemens A.G. (Germany), Simko Ticaret Sanayi A.S. (Turkey), Koch Transporttechnik (Germany) and GAMA HOLDING (Turkey)
Project Value400 MEUR
Project LocationKangal, Turkey
Project StatusCompleted and commissioned in 2000